Background

The Lutak Dock was constructed by the U.S. Army in 1953 for the purpose of building and supplying the Haines-Fairbanks pipeline, a Cold War era project that delivered fuel to military bases in the interior. The Army designed the cellular sheet pile dock to receive massive amounts of materials for the construction of the 626-mile pipeline and associated tank farm.

The pipe was unloaded onto the Lutak Dock and then loaded onto logging trucks for distribution along the route. (see image below)

Unloading and stockpiling British Pipe at Haines

In 1977, after the pipeline was decommissioned, the Army gave the Lutak Dock to the City of Haines. The cathodic protection system that the Army maintained and operated over the years was turned off after the Haines Borough took ownership of the dock. The borough couldn’t afford the costs associated with operating the system, and the dock deteriorated over the years.

Ownership of the dock is split between the Haines Borough and the state. In the 1980s, a roll-on/roll-off ramp (RO/RO) was installed on the face of the borough-owned side of the dock, which freight Alaska Marine Lines (AML) used to deliver freight. A few years later, Totem Oil installed the fuel pipes across the Lutak Dock at their own expense. Fuel company Delta Western purchased Totem Oil in the mid 1990s.

The Lutak Dock has two users, fuel company Delta Western and freight company Alaska Marine Lines. Delta Western delivers fuel 15-20 times per year. Alaska Marine Lines (AML) delivers groceries and other freight once per week.

AML’s old RO/RO was attached to the face of Lutak Dock.

By 2018, things looked dire. With the dock failing, Haines needed to find a safe and reliable way to continue to receive freight. According to a 2018 report published by HEDC:

“Should Lutak Dock not be repaired and suffer a failure that renders the dock inoperable, Haines residents would likely see significant freight disruptions and price increases. While there is no clearly defined contingency plan, the two most likely options are to rely on the Alaska Marine Highway System and/or barge freight to Skagway and then truck to Haines. In contrast to AML, Delta Western appears to be in a better situation as it would likely be able to continue to use its tank farm and related fuel infrastructure even in the absence of repairs." (2018 Economic Baseline Report, pg. 46)

PROBLEM SOLVED

In 2020, AML paid $2.6 million for the construction of a new Roll-on-Roll-Off dock (RO/RO) on the Borough-owned tidelands adjacent to the Lutak Dock. All of the town’s freight has been delivered via the new RO/RO since 2020. The Haines Borough and AML have a 30-year lease for this arrangement. According to the agreement, use of the ramp is not restricted by AML and is open to other users.

AML’s new RO/RO dock is not attached to the Lutak Dock.

The Lutak Dock Replacement

After over a decade of failed grant requests, the Haines Borough is moving forward with a $25 million replacement of the Lutak Dock, despite the installation of a new RO/RO freight ramp adjacent to the dock in 2020. The cellular sheet-pile dock, which was built in 1953, is failing - but the dock has been closed since 2020. What needs to happen at the dock to ensure current operations can continue safely? We don’t know, because dating back to at least 2010, dock renovation efforts have been centered around the expansion or redevelopment of the dock as a deep-water port.

The dock project approved by the community was to rebuild the dock for safety. Many are still under the assumption that we need a new dock to receive our groceries, and the recent narrative presented to the community is that the replacement of the Lutak Dock is solely to meet local needs. But in 2021, the borough submitted a RAISE grant application that referred to the transshipment of ore at Lutak dock.

This deepwater port is a year-round, sheltered harbor with excellent road connectivity and the potential to develop spacious upland storage that could support the maritime services industry, bulk cargo handling, and transshipment of ore, timber, bio-mass/woodchips, and rock/gravel.

And in February 2022, the borough submitted a state CAPSIS request for $3.2 million (for the 20% match required for the RAISE grant), which stated:

"...The Lutak Dock also plays a crucial role in the economic viability of the region. Key mineral mines in the Yukon territories, and other northern regions need access to maritime shipping as a cost effective way to bring their products to market.”

March 24, 2022 Ports and Harbor Meeting

The scope of the project (load weights, size, vessel capacity) has many concerned, especially after a controversial Port and Harbor Advisory Committee meeting in which seven Yukon mining representatives attended to discuss the design plans and future use of the Lutak Dock. Yukon mining representative made it clear that they would need the new dock by 2024, which is also the deadline the borough proposed for project completion — well ahead of the federal granting agency’s September 2029 deadline.

Listen to the audio clips from the meeting:

 

The Old Design

R&M’s old 3-Phase design would demolish the existing cells, adding an elevated platform in Phase 3 that would provide ship-to-shore access. This is the design the borough used to apply for the 2021 federal RAISE grant — this is the design that was approved by MARAD (the federal granting agency) when they selected the Haines Borough for a RAISE grant award in November 2021.

The old design would have cost $3.75 million per decade in maintenance costs.

The New Design

The Haines Borough is moving forward with the progressive design build of the Lutak Dock. They have chosen Turnagain Marine Construction for the design-build of the Lutak Dock, and R&M Consultants (the firm that developed the old design) as the Owner’s Advisor.

In July, Turnagain proposed a new concept for the Lutak Dock Replacement that would retain the dock’s original footprint. It is similar to a design R&M Consultants proposed in 2017, which would have cost $60 million.

Turnagain says their design is only $25 million because existing cells would be “encapsulated” with no demolition or excavation involved. They propose to encapsulate the existing cells and drive 60” or 42” diameter steel O-Piles for a new wall, backfilling the area between the new wall and existing cells. Rather than demolishing the old cells, which R&M’s design would have done, Turnagain plans to retain the 700 ft dock face, calling for a load limit of 2,000 pounds per square foot.

Their new design would extend the face of the dock seaward and out of line with the ferry’s side of the dock, potentially interfering with ferry operations. It would also interfere with AML’s newly installed RO/RO. According to the borough, these details have not been flushed out yet.

There are a lot of issues with Turnagain’s design, including the fact that the anticipated maintenance costs for the new design have not yet been determined. Considering that taxpayers will be on the hook for these costs, we deserve to know that information before it’s too late.

The Planning Commission will review the 65% design on February 9, 2023.

 

Action Items

Borough code requires Turnagain's design proposal to be seen by the Planning Commission at the conceptual stage, as well as at 35%. But Turnagain's design was not seen by the Planning Commission at the conceptual stage. The first time the Planning Commission will see the design is at the 35% stage — at their meeting on December 8th. You can attend that meeting via zoom.

You can also submit comments by contacting your local representatives here and here.

Questions for your Haines Borough representatives:

  • What are the maintenance costs associated with Turnagain’s new design?

  • The steel pilings Turnagain plans to use for the new wall aren’t galvanized. The pilings would be epoxy coated and sacrificial anodes would be installed. Turnagain estimates the anodes would need to be replaced in 15-20 years. How expensive would replacement anodes be?

  • What do the dock’s current two customers, Alaska Marine Lines (AML) and Alaska Marine Highway System think about Turnagain’s new design, which would push the dock face out, potentially interfering with ferry operations and forcing the relocation of AML’s new RO/RO?

  • Why wasn’t the Lutak Dock listed as critical infrastructure in the HB’s 2009 or 2015 Hazard Mitigation Plan?

  • The Borough’s RAISE grant application lists key contributers, including Constantine Metal Resources. Who are the stakeholders of this project?

  • The deadline set by MARAD (federal granting agency) for fund liquidation is September 2029. Why is the deadline for project completion (determined by the borough) December 2024? What's the rush?

We want to know what you think: Take our anonymous dock survey

Make your voice heard

Tell the Yukon Mining Industry: We Will NOT Embrace You

 

News

Keep Yukon ore out of Haines, Alaska, conservationists say

Julien Gignac · CBC News · Posted: May 18, 2022

Haines Chamber facilitates AIDEA Lutak Dock financing discussion

Kyle Clayton · Skagway News · May 14, 2021

State-owned corporation considers shuttering Skagway ore terminal, building a new one in Haines

Henry Leasia · KTOO · April 17, 2021

 

What are the risks?

Image taken from The Emergency Operations Center's Public Service announcement prepared for the town of Haines by a GeoHazard team on the ground. 12/8/2020

The Lutak corridor was among the Areas of Concern in the Geohazard assessment after the December weather disaster.

Understanding of future extreme weather events, seismicity, localized tsunamis and other potential hazards should guide any future developments such as trucking and shipping ore over Lutak Dock.

The Chilkat and Chilkoot commercial and subsistence fisheries would be directly at risk-- hooligan, herring, and salmon are sensitive to contaminants.

The haul route to the Lutak Dock would go directly through town. Big, noisy ore trucks would drive through town at all hours, emitting fugitive dust, driving down property values, and polluting our subsistence food sources & watershed.

Skagway Ore Terminal

The municipality of Skagway, Alaska, won't be renewing its lease for the ore dock owned by Alaska Industrial Development and Export Authority (AIDEA). AIDEA leases the ore facility and ore loader to White Pass and Yukon Route Railroad. owns the ore facility and the ore loader but sublets leases the land and part of the dock they sit on to White Pass and Yukon Route Railroad. The municipality of Skagway plans to take possession of the ore dock in 2023 when the long-term lease with White Pass expires.

Skagway is upgrading its port infrastructure to accommodate bigger cruise ships, with plans to put an increasing focus on seasonal tourism.

Skagway’s Contaminated Harbor

In the mid-1980s after the South Klondike Highway opened, trucks came through town every 30 minutes 24 hours a day 362 days a year hauling lead and zinc ore concentrate.

Finally, in 1988, light was shed on the lead contamination in Skagway. Blood tests were drawn from Skagway residents… According to the report and the standards at the time, none were above a level of concern. But if held up to today’s standards, most of those children would have been in the top 2.5% of children tested for lead levels in blood nationally.

A state memo referenced by The Associated Press in 1988 said that the “Bottom sediments in the Skagway Harbor have been found to be among the most toxic in the world.”

Clean up of Skagway’s contaminated harbor has stalled yet again

KHNS | Mike Swasey | Jun 24, 2021

Skagway harbor cleanup raises questions about water quality and seafood safety

KHNS | Posted by Mike Swasey | Apr 1, 2022